New Albany High School
Staff Input per Category
- Functionality/Efficiency/Flexibility:
Fieldhouse, science upgrades, additional & upgraded athletic facilities
(lockers, fitness, wrestling, coach offices, etc.)
- Collaboration/Connections: Flexible
furniture, more conference rooms
- Accessibility/Special Programming: Chrome
book charging in classrooms, wholistic ADA accessibility
- Comfort & Well Being: Finishes/paint/carpet/furniture/aesthetics,
electrical/lighting upgrades, bottle fill stations, natural light, outdoor
classroom, roof leaks, more restrooms/stalls, HVAC upgrades, acoustics between
rooms
- Safety & Security: Pest control,
exterior lighting upgrades, building entry control, stairways narrow/poor
treads
Conditional Assessment (Overall Suitability: 72%)
Conditional Assessment Summary
- Site: Items that scored poorly include size of
site, lawn/landscaping, traffic flow, mechanical courtyard, site lighting,
overall tennis courts condition, football stadium shot put, discus, goal posts,
no visitor bleachers, practice field, no JV baseball or softball field, band
practice lot, SW lot, NW lot asphalt, curbs and walks, concrete steps/rails at
older building areas.
- Architectural: Building
exterior walls are in good condition. Windows are in good condition with
exception of many of the operable windows are cloudy due to broken seals.
Roofing consists of 3 different types (spray foam, standing seam metal and EPDM
membrane) and overall is good condition. Interior is in good condition
with new carpeting throughout.
- Interiors: The carpet in hallways and main
floor offices, installed in 2021-2022, is in good condition. The VCT flooring
appears worn but is expected to remain functional for years. Roof leaks are
present in various areas of the building. Wall paint and trim conditions vary
room by room, with some rooms needing fresh paint for doors and trim while
others are in good shape. The commons area underwent renovations between 2019
and 2022, receiving new LVT flooring and versatile seating options. The media
center was renovated in 2019 & furnishings there are in excellent
condition.
- Mechanical: The Central Plant needs a Cooling Tower, a
water-cooled Chiller, and two pumps. The boilers are in good condition.
Ten Air Handling Units are in poor condition and should be replaced. The other
six Air Handling Units are in fair condition for their age and are candidates
for refurbishment. Exhaust fans are aged and should be considered for
replacement with modern direct drive fans. Classrooms are conditioned by aged
Powered Terminal Units. There is an opportunity to revise and improve the system
at the classroom level.
- HVAC Controls: Andover Continuum / Infinity controls are outdated. The graphics time out and, in some cases, do not display properly. Recommend full replacement in the next 3-5 years in conjunction with HVAC mechanical renovation.
- Electrical: (2) generators, (1)
NG, 1980 is fair-poor, (1) Diesel, 2000 in good; distribution equipment from
1980 is fair-poor, 2000 is good; fire alarm system, 2000, is beyond end of
life; LED in Gym (with dimming), Cafe & high volumes, fluorescent
everywhere else; exterior lighting is LED w/ some leftover HID being
retrofitted to LED, LED wall packs; automatic interior lighting controls only
in media center & classrooms, manual controls elsewhere; exterior lighting
has BMS controls.
- Plumbing: Incoming services
appeared to be adequate and in good operable condition. Domestic distribution
system and insulation was in good condition throughout. Existing water heater
in main mechanical room appeared to be in repair or being replaced at time of
assessment. Cross flow issues were mentioned during the assessment from staff
at all mop basins resulting in malfunction of faucets. Main gas service showed
signs of heavy/moderate corrosion. Fixtures appeared in good condition
throughout. Most lavatory faucets and some flush valves did not function as
intended and need replaced throughout. Most handwashing stations throughout
need a mixing valve to prevent scalding risks. Classroom sinks have moderate
scale build up & wear. 3 comp. sink in kitchen has multiple code violations
for waste piping connections.
- Technology
- No electronic door monitoring. Staff walk around
building at day’s end to check doors.
- Video surveillance. A lot of blind spots around the exterior
of the buildings.
- Classroom A/V. In working condition but getting dated. They are planning projects to update.